|
Downtown Expansion
A Hotel Grows in Brooklyn to Meet
Demand
by Diane Greer
The
largest hotel in Brooklyn is getting even bigger.
When Queens-based Muss Development hatched plans for the
Brooklyn Marriott Hotel in 1996, it dreamed up a larger project.
But financial constraints limited the scope of the initial
project, and the seven-story hotel that it eventually built
and opened in 1998 encompassed 350,000 sq. ft. and 376 rooms.
Now, a new 24-story, $77 million addition, rising adjacent
to the existing hotel, will complete the vision. The project
is slated for completion in August.
"We are gratified that the expansion is happening under
the right circumstances, on our own terms, when we wanted
it to happen," said Jason Muss, a principal at Muss Development
and son of Joshua Muss, the CEO and president who spearheaded
the initial development.
The existing hotel on Adams Street in downtown Brooklyn is
part of the 1.5-million-sq.-ft. Renaissance Plaza development,
which includes 900,000 sq. ft. of office space and a parking
garage with 11,000 spaces. That infrastructure gave the hotel
an early boost, said Sam Ibrahim, general manager for the
hotel.
"The Brooklyn Marriott met with instant success when
it opened," he added.
Ibrahim also credits the property's proximity to Manhattan
and features such as the fourth-largest ballroom in the city
as key ingredients in the hotel's positive performance.
Still, the hotel was hamstrung from using the full capacity
of its meeting facilities because it could not accommodate
large groups that needed 400 to 500 rooms for their conferences.
"We cannot use every room in the facility for large
groups and thus disappoint our loyal local customers,"
Jason Muss said. "By adding the rooms, we are basically
allowing the hotel general manager and staff to use the hotel
in the best way possible."
The new 190,000-sq.-ft. addition will include 282 guest rooms,
as well as meeting rooms and a concierge lounge on the top
floor that doubles as a party room. The lounge, which includes
two outdoor balconies, offers spectacular views of Manhattan
and the surrounding area. Two below-grade stories will house
retail space and conference support for the facility.
The addition takes up a lot that had contained a city-owned
parking garage, which the developer demolished. Excavation
of the site required some shoring of adjacent structures but
was otherwise routine, Muss said.
The new poured-in-place concrete building sits upon a traditional
mat foundation. The exterior of the first three floors will
be clad in limestone, while the higher floors will have exterior
insulating finish system panels. The EIFS panels, made from
polystyrene foam board with a textured acrylic finish, aim
to resemble a limestone finish by mixing ground limestone
into the mix, said Don Sandy, design architect and chairman
emeritus of SB Architects of San Francisco, the project's
architect.
Muss said windows are installed into the EIFS panels at the
factory, and finished panels are welded onto the building
at the jobsite. A Muss affiliate served as general contractor
on the project.
The "postage stamp"-sized lot dictated the design,
calling for a tall, thin building with each guest floor housing
16 rooms, Sandy said. He designed the structure to serve as
a transition between classic architecture on one side of the
structure and the modern Renaissance Plaza complex, with the
existing Marriott, on the other side.
"The exterior takes a modern classical approach with
solid materials rather than glass curtain wall," Sandy
added.
A two-story pedestrian bridge will link the new addition
to the existing hotel, crossing above the promenade leading
to Metrotech, a nearby office complex in Downtown Brooklyn.
Sandy said he drew his inspiration for the bridge from the
art nouveau style of the subway entrance at Union Square in
Manhattan.
"It just dawned on me, why shouldn't we make this a
park-like bridge out of metal, replicating the medium green
color of the subway entrance," Sandy said.
The first level of the bridge connects the lobby of the existing
hotel to the addition. The second level of the bridge will
be used for service functions.
The contractor team topped out the structure in March, and
in spring, the construction team was installing exterior panels
and working on the mechanical, electrical, and plumbing hookups
within the structure.
"We contemplated this addition when we built the original
Renaissance Plaza," Muss said. "Structural, mechanical,
and service items were predesigned and installed into the
original building. The utilities for the addition connect
to the existing base building underneath the structure."
The new building also has a gearless Otis Gen2 elevator system,
which does not use a machine room. Instead, its machine and
controller are installed at the top of the hoistway, Muss
said.
"Only two buildings in New York have these systems,"
he added. "It has been a good system for us, so we are
going with it again."
All the new rooms in the hotel will take advantage of Marriott's
latest design innovations, including 32-in., flat-panel TVs,
bathrooms with enhanced natural lighting and round shower
stalls, and tiled entry foyers.
"We are also going to be redoing all our existing rooms
to dovetail with what we are doing in the tower," Muss
said.
The construction effort is not disrupting services at the
hotel, Muss said. Heavy work on the site generally takes place
during the middle of the day, when most guests are out of
their rooms. Also, most of the existing hotel rooms are located
on the north side of Renaissance Plaza, while the new addition
is located on the south side of the complex.
"We have been able to maintain business levels and everything
is operating as usual," he added.
Key Players
Owner: Muss Development,
New York
Architect: SB Architects,
San Francisco
Contractor: Muss Brooklyn
Development Corp., New York
Structural Engineer: Wayman
C. Wing, New York
Site, M-E-P Engineer:
Lehr International Associates, New York
|