|
Current Work
Track Upgrade Projects Are a Critical
Link
by Katherine S. Robertson
The Metropolitan Transportation Authority's
ambitious $6.3 billion East Side Access project is virtually
a game of dominoes. The plan to connect commuter rail service
from Long Island and Queens to Manhattan's Grand Central Terminal
by 2012 has required the expansion, construction, adaptation,
and realignment of railroad yards, tracks, and signals across
three boroughs.
A critical element of these sequenced projects is a pair
of track and signal upgrade and installation projects in Queens
and Manhattan by MTA's Long Island Rail Road and Metro-North
Railroad divisions, which will share Grand Central. They are
working with the agency's Capital Construction Co., the lead
unit on the project.
The Manhattan work is at the East Yard, where on 15 acres
of Grand Central's lower level, more than 20 ft. below street
surface, crews are reconfiguring track, installing new signals
and power cables, and modifying and replacing an existing
Central Instrument Location system with a microprocessor-based
interlocking system. The yard will continue to serve primarily
as storage for excess rail cars that Metro North brings in
during its morning peak but cannot route out of the station.
The East Yard scope calls for installing 11 pieces of special
track, restoring and repairing the third rail, and installing
a new signaling system to support the new track configuration,
said Bob Magnifico, director of program implementation for
MTA Capital Construction.
"We put in connections to improve access and routing
within the East Yard to give more operational flexibility,"
he added.
The signaling will allow MTA to take individual system segments
out of service instead of closing down an entire leg.
"It's an efficient use of power distribution,"
added Mike Daniels, a senior project manager for MTA Capital
Construction. "It's safer and can be done remotely."
In Queens, meanwhile, LIRR, Amtrak, and contractors will
finish adding track switches, power, and signals next month
in a project that will provide direct access to the $75 million
Arch Street Yard maintenance and storage facility, which was
completed in the spring.
The work at the portals of tunnels that run under the East
River involves reconfiguring the track, installing a signal
system that will coordinate traffic in and out of the facility,
and adding a third rail for electric-powered trains. The facility
currently only supports diesel locomotives, Magnifico said.
The job encompasses 6,000 ft. of track.
Amtrak is collaborating on the work because Arch Street connects
to tracks serving the carrier's nearby Sunnyside Yard, said
Sam Zambuto, an LIRR spokesman. The $12.1 million job - with
$8.3 million from LIRR and $3.8 million from Amtrak - entails
Amtrak performing work on its property, including installation
of a third rail, additional switches to allow LIRR trains
to cross its yard, and a catenary, or overhead electrical
cable. LIRR is installing switches and electrifying track
on other portions.
"The difficult part is that the work is so closely related
to active train operations," said Albert Bast, a vice
president of San Francisco-based URS Corp. and a member of
the board of control for the East Side Access program manager,
a joint venture between URS and San Francisco-based Bechtel
Infrastructure. Bast added that project coordination is also
a challenge, because much of the work is taking place at night
or on weekends to avoid peak rail usage times.
At the end of the day, Bast said, MTA Capital Construction
will issue from 70 to 90 third-party and force account contracts,
all of which interface with other parts of the massive rail,
tunneling, and infrastructure project.
|
Key Players
Arch Street track upgrades
Owner: Metropolitan
Transportation Authority Capital Construction Co.
Contractor: Long Island
Rail Road and Amtrak force accounts
Grand Central East Yard track
upgrades
Owner: Metropolitan
Transportation Authority Capital Construction Co.
Contractor: Metro-North
Rail Road force account
|
|