|
An Engineering Feat
Digging Begins on Manhattan Section
of City Water Tunnel No. 3
by Natalie Keith
Though few will ever see it, deep beneath Manhattan's streets
is a $750 million "engineering feat of gigantic proportion."
Since last fall, workers have been digging the Manhattan
section of City Water Tunnel No. 3, a project that is being
described as the largest public works project the city has
ever undertaken. The size and length of the tunnel, its sophisticated
control system, the placement of its valves in special chambers,
and the depth of excavation all make this a challenging job
to complete.
"Though rarely seen by the public, this project will
increase our water systems reliability and will instill a
sense of security in our city's ability to provide essential
services for future generations," said Mayor Michael
Bloomberg.
Located 550 ft. under the streets of Manhattan, the tunnel
will deliver safe drinking water to city residents. The section
of the tunnel currently under construction originates from
30th Street on the west side of Manhattan and will run downtown
to the Holland Tunnel. A second section will loop north up
the west side to the Lincoln Center area. This 8.5-mile section
of the tunnel will cost $750 million and will be activated
by 2011.
Planning for City Tunnel No. 3 began in the early 1960s with
construction starting in 1970. The 60-mile-long Tunnel No.
3 is being constructed in four stages and is expected to be
completed by 2020 at a total cost of $5.5 billion to $6 billion.
The project is being financed through the sale of water bonds
and the collection of water and sewer charges, according to
the city's Department of Environmental Protection, which is
overseeing the project.
Stage 1, completed in 1998, runs 13 miles from the Hillview
Reservoir in Westchester, through the Bronx, Northern Manhattan
and Queens. It cost approximately $1 billion and is already
delivering drinking water to parts of these boroughs. Eventually,
the Manhattan leg will be connected into the Stage 1 portion
of the tunnel.
Stage 1 is a 24-ft. diameter concrete lined pressure tunnel
that steps down in diameter to 20 ft. As water travels along
this route, it will rise from the tunnel via 14 supply shafts
and feed into the distribution system. Three of the four unique
subsurface valve chambers have already been built to allow
the connection of future stages of the tunnel without removing
the water or taking any other stage of the tunnel out of service,
according to the DEP.
The three valve chambers are located in the Bronx at Van
Cortlandt Park and in Manhattan at Central Park and Roosevelt
Island. Each valve chamber contains a series of 96-in. diameter
conduits with valves and flowmeters to direct, control and
measure the flow of water in sections of the tunnel, according
to the DEP.
The first section of Stage 2, the Brooklyn-Queens portion,
is completed and will be activated by 2007. This 10.5-mile
leg of the tunnel runs from Red Hook, Brooklyn to Woodside
and Astoria, Queens.
"The activation of Stages 1 and 2 of Tunnel No. 3 will
provide the system with the ability to bypass one or both
of City Tunnels No. 1 and 2," said DEP commissioner Christopher
Ward. "Operation of the new tunnel will allow for inspection
of the older tunnels for the first time since they were put
into operation in 1917 and 1936 respectively."
The tunnel will require 79,000 tons of concrete to complete
and the amount of rock displaced during excavation will be
approximately the size of a football field piled 250 ft. high.
So how are workers able to remove that large amount of rock?
They're using a tunnel boring machine, a mechanical rock excavation
technology never before used in City Tunnel No. 3. The TBM,
also called the "mole," was lowered in sections
and assembled at the bottom of the shaft in a short section
of tunnel called the "bell out." The TBM is about
70 ft. long and is supported by 700 ft. of trailing gear,
according to the DEP.
It is a Robbins 1215-257 hard rock-main beam type tunnel
boring machine and uses a rotating cutter head containing
27 17-in. diameter disc cutters to crush the rock. The disc
cutters push into the rock under a thrust load of 1.9 million
pounds and crush the rock into small fragments. Four 450 horsepower
electric motors rotate the cutter head at approximately 12
revolutions per minute, according to the DEP.
The crushed rock, or muck, is removed from the face of the
tunnel through the TBM and over the trailing gear by conveyor.
The conveyor discharges the muck into muck cars. Trains of
four muck cars pulled by locomotives transport the muck through
the bored tunnel to the access shaft, where the muck is transferred
and raised to the surface by a vertical conveyor belt, according
to the DEP.
Initial excavation will be south of the shaft. After the
south portion is completed, the TBM will be backed out to
the shaft and turned around to do the north portion of the
tunnel. It is anticipated that the TBM will excavate bedrock
24 hours a day, five days a week, at a rate of 75 ft. per
day, according to DEP.
|