Ferry Construction Steams Ahead
With the Rebirth of Ferries,
Construction Picks Up
by Jason Feldman
Ferries have a long history in New York City.
They were once the dominant form of cross-river and harbor
traffic - until the Brooklyn Bridge opened and ferry traffic
began a long, slow decline.
Ferries made a small comeback in the mid '80s, but it wasn't
until after the terrorist attacks of Sept. 11, 2001, when
bridges and tunnels were closed and Manhattan island was isolated,
that the revival in ferry traffic began in earnest.
During Sept. 11, the ferries successfully evacuated 160,000
people from the tip of Manhattan. The New York Times called
it the largest one-day water evacuation ever.
With the destruction of the PATH tubes leading to Lower Manhattan,
NY Waterway has seen its daily passenger trips increase from
33,000 passengers to 60,000 said company spokesman Pat Smith.
"We are not looking to capitalize on a tragedy and we
expect a fall-off in ridership after service has been restored
to the PATH," Smith said. However, even with the completion
of a reconstructed PATH tubes across the Hudson, Smith said
NY Waterway is projecting an eventual increase of up to 70,000
passengers a day.
With this new demand, construction around the metropolitan
area of ferry infrastructure is on the upswing.
Currently, there are five major projects under way or planned
to get under way soon. They include the Whitehall Ferry Terminal
in Lower Manhattan; West Midtown Ferry Terminal at Pier 79
on West 39th Street; St. George Ferry Terminal in St. George,
Staten Island; Port Imperial Ferry Terminal in Weehauken,
N.J.; and the historic Hoboken Ferry Terminal in Hoboken,
N.J. Work is also planned on numerous slips along the East
River.
Port Imperial Ferry Terminal
This new terminal in Weehauken, N.J. is envisioned as a "lantern
in the river," by Jordan Gruzen, senior partner of Gruzen
Samton LLP, the project's New York-based architect.
The $30 million project will replace an existing facility
that is 1,000 yds. south of the Port Imperial site. The new
33,000-sq.-ft., two-story, terminal building will include
a 21,000-sq.-ft. main waiting area, numerous passenger amenities
and an estuary garden at the entrance.
The building will be placed on top of a pile-supported concrete
platform built over the Hudson River. Connecting to the terminal
building will be two floating platforms that are 100 ft. long
by 35 ft. wide that will contain the four ferry slips. The
ferry slips have been designed to be ADA compatible. In addition,
they have the ability to move up to 7 ft. with the water.
Rising from the platform will be the main terminal building
that will have a steel frame with a curtain wall made of low
E glass as the envelope system, said Ivan Ilyashov, a Gruzen
Samton partner. The use of glass will enhance the views of
New York and will have the effect of making the building glow
at night.
The final design has been approved by the owner, N.Y. Waterways,
and is undergoing an extensive environmental review. Gruzen
said that dredging could begin in fall 2003 with completion
coming in 2005. Once it is built, New Jersey Transit will
buy the building for $1 and lease it back to NY Waterway to
operate.
Historic Hoboken Ferry Terminal
The historic Hoboken Ferry Terminal in Hoboken, N.J., south
of Weehauken, has recently been funded by the Port Authority
of New York and New Jersey.
The $125 million project will restore the ferry slips at the
1907 building.
As part of an agreement with NJTransit, the PA will provide
up to $8 million to pay for the design work for the six slips
in the terminal. The PA will also provide an additional $44
million from its capital program, and the Federal Transit
Administration will contribute $27 million, which will permit
the initial phases to begin.
Work at the terminal will include:
- Reconstruction of a portion of building's substructure and
superstructure.
- Construction of ferry service ticket offices and a waiting
area.
- Restoration of the copper fascia and lighting on the exterior
of the building.
- Waterproofing and insulation of the exterior walls near
the ferry slips.
- Restoration of the interior finishes of the ferry terminal
area.
- Utility and marine work to support the ferry operation.
St. George Ferry Terminal
The New York City Economic Development Corp. has put out a
$103 million contract to restore the Staten Island Ferry terminal
building.
"Right now it feels like a high school gym," said
Ken Druker, design director of HOK New York, the project's
architect. "The idea is to create a state-of-the-art
intermodal terminal that will be the first LEED-certified
transportation project in the country."
The work includes the renovation and expansion of the ferry
terminal, the creation of a new waiting room, a north terrace
connection to a new ballpark and a new front door.
The roof of the terminal building will be raised to transform
the main waiting areas into a light and airy space with clerestory
windows on all sides to let in natural light. A 40-ft.-high
glass wall along the waterside will provide a view of the
harbor.
A new curtain wall will replace the existing brick. A new
terrazzo floor will be placed in the concourse, a skylight
will be added and all new signage will provide real-time information
on transit departures.
To obtain LEED certification for the building, a living roof
will be placed over the central plant wing, which will be
watered by rainwater and pumped by power from photovoltaic
cells. A major new feature will be a new gateway arch that
will welcome visitors and commuters to Staten Island. "It's
iconic, and it's a reference back to the bridges that lead
to Staten Island," Druker said.
A new HVAC system will introduce air conditioning in the summer
and heat in the winter. Other new systems will include sprinklers
and redundant power.
The project is 40 percent complete.
Whitehall Ferry Terminal
On the other side of the Staten Island Ferry lies the Whitehall
Ferry Terminal in Lower Manhattan. This facility was damaged
by a fire in 1992 and is currently undergoing a $145 million
phased reconstruction.
"The final phase, phase three, is proceeding," said
Mazir Mir, vice president of capital programs for the New
York City Economic Development Corp., the project's owner.
"Slips two and three are operational and slip one is
now being worked on.
"By next year it should be complete, roughly around the
same time as the St. George Terminal."
The temporary waiting area is also being demolished to make
way for grand, new a 19,000-sq.-ft. waiting area.
Sitework for Peter Minuet Plaza, adjacent to the terminal,
is also under way. That work consists of reconfiguring the
traffic islands and the connecting streets to safely accommodate
pedestrians. And for the first time, a connection to the 1
and 9 trains will be established on the inside of the terminal
building.
West Midtown Ferry Terminal at Pier 79
The future home for the $40 million West Midtown Ferry Terminal
is Uptown at West 39th Street at Pier 79.
Construction began in January on a new ferry terminal that
will wrap around the ventilation towers for the Lincoln Tunnel.
"The unique thing is we could not drive piles because
the Lincoln Tunnel was below the site," said Mark Patterson,
project manager for Skanska USA Building, the project's general
contractor.
The developer of the terminal is the New York City Economic
Development Corp.
The site previously contained a steel shed that was used for
storage and parking of shuttle buses. "We demolished
that and we are currently constructing the relieving platform,"
Patterson said in June. "The actual construction of the
33,450-sq.-ft., two-story, glass enclosed structure will start
(later) this summer."
The structure will contain the waiting room, retail, a café,
administrative offices, outdoor recreation areas and a taxi/bus
drop-off area. Barges will be floated in to create the six
ferry slips. The project is expected to be completed in fall
2004.
Ferry Slips
While the bulk of the work will be performed on terminals
along the harbor and the Hudson River, there is an approximately
$22 million program organized by the EDC to upgrade numerous
slips along the East River.
Slips at the Battery Maritime Building, East 34th, East 62nd,
East 75th and East 90th streets will be upgraded over the
next year.
Farthest south is the Battery Maritime Building, which is
undergoing a $2.3 million contract to renovate the entrance
and to improve the waiting area, said Paul Januszewski, assistant
vice president of NYCEDC. He said that a separate contract
has been awarded to renovate the exterior of the building.
At East 34th Street, which Januszewski regards as the hub,
a 3,000-sq.-ft. building will be constructed on a renovated
pier. The building will include a protected waiting area and
passenger amenities. Barges will be installed to create the
docking facilities.
For East 62nd and East 75th streets, a barge will be constructed
that will attach to the bulkhead.
East 90th Street has an existing pier that was damaged by
fire. A new barge with a small shelter and a ticketing booth
will be placed by the pier and new lighting and landscaping
will be installed at all of the sites.
And in New Jersey, a new slip at the Newport neighborhood
of Jersey City just won site approval. The approval helps
to pave the way for construction of a 1,500-sq.-ft building
near the ventilation tube for the Holland Tunnel.
Future Work
NY Waterway spokesman Smith said the future of ferry travel
seems to be bright. He said that the key to ferry travel in
the region is dependent on getting people out of their cars.
"One of our most successful new ferry routes is from
Belford (N.J.) to the tip of Manhattan," Smith added.
"Harry Larrison, the freeholder director, had a vision
to seek money for a ferry terminal with a parking lot and
then put out a request for proposals from ferry operators.
We responded and now we have 2,500 passenger trips a day generated
from that route."
He said NY Waterway is looking up the Hudson River for future
sites that can provide free or low-cost parking and also are
convenient to the Manhattan bus network. The Rockaways are
also being looked at, Smith added.
Smith said the Port Authority has a plan on the books to build
a terminal building and parking lot along the eastern coast
of Staten Island.
"We have clocked a ferry from that location to Pier 11
at Wall Street at 22 minutes," he added.
Although it would be roughly the same route as the Staten
Island Ferry, Smith said he does not view it as competition.
"We are not in competition with mass transit," he
said. "We are trying to get people out of their cars."
|