Iona Adds Two New Residence Halls
First Step in Major Campus Expansion
by Jason Feldman
Iona College began the transformation of its New Rochelle,
N.Y., campus in June 2002 with the construction of two new
residence halls.
However, getting started wasn't easy. Iona College, the project's
owner, at first decided to bring in a Texas-based construction
firm to do the job.
"The cost of construction is lower in Texas and unfortunately
they did not take into account how much the cost of construction
was in New York," said George Fountaine, director of
facilities management for Iona. "Their budget was far
below the cost of construction in New York. When they got
their numbers back, it still did not work."
So it was back to the drawing board. Eventually, the Catholic
college with an enrollment of 2,800 students that was founded
by the Christian Brothers 63 years ago decided to get a bond
with the Dormitory Authority State of New York and settled
on the Pearl River, N.Y.-based Holt Construction Corp. as
construction manager.
"One project that Holt Construction Corp. was working
on - Pratt University - was close to what our project was
going to be," Fountaine said. "It was in a tight
spot and the logistics were not easy. It matched what we were
going to do so we selected Holt."
When Holt was brought on, it had only one year to complete
the residence halls.
Getting Started
The two residence halls are located on a narrow site hemmed
in by other Iona facilities. The first step was to place the
new structures so they would share a common entrance with
an existing 10-story dormitory.
"To create the plaza, we had to site one building perpendicular
to the other," said Anthony Pucillo of Anthony Pucillo,
AIA, the project's architect of record.
Once the location on the site was settled, some utilities
had to be cleared before work could start. "We had to
move water and sewer lines on the site itself," Fountaine
said. "We asked the city to do that before construction
started, which they approved."
With the utilities relocated, work began on the excavation
for the foundation. It was not an easy dig.
"The cellar floor slab is 2 ft. below the water table,
and on top of that the building was on a sloping rock, which
necessitated the construction of a mat slab to allow for uniform
settlement of the building," said Robert Blum, senior
project manager for Holt Construction Corp. The excavation
went down 14 to15 ft. deep.
When the depth was achieved, water infiltration became the
biggest problem. "What we did was install a concrete
rat slab covered with waterproof 60 mill HDPE membrane,"
Blum said. "Then we built an asphaltic protection board
over that. And then we poured an 18-in.-thick mat slab over
that to form the foundation and control the hydrostatic pressure."
The waterproofing was carried up and over the foundation walls
and wedded to a waterproof membrane at the top 3 ft. of the
foundation.
To further prevent water infiltration a bathtub (slurry wall)
was built around the perimeter of the buildings. Additionally,
since bathrooms were located in the cellar level, it required
the installation of pumps below the cellar floor elevations
and they had to be included in the bathtub.
Because of the extra work on the foundation, the pouring of
the structural concrete stretched into this year's severe
winter.
To combat the cold and precipitation, "We had to provide
protection and heat for the building while we poured the 7.5-in.
reinforced-concrete flat-plate floor slabs and columns,"
Blum said.
The cold weather also would affect the strength of the concrete,
so "a 6,000-psi concrete was used, which allowed us to
reach our 4,000-psi strength early and allowed us to remove
the shoring and forms and reshore the building and move on
the next floor," he added. Blum said the team was able
to achieve a five- to six-day cycle.
"This past winter was one of the most brutal in terms
of temperature and snow, and even though we lost a couple
of days, we are still on time and budget," Fountaine
said.
Logistics Play Key Role
"Logistics would have been a nightmare if we did not
plan for it," Fountaine added. "There was an existing
dorm that exited right into the site. In addition, the buildings
were located on two small roads and this could have led to
a pedestrian problem as well as a traffic problem."
A pedestrian bridge was built from the existing dorm's entrance
to the front of the campus. At the same time, Iona struck
an agreement with the city to provide a police officer on
campus to direct pedestrians away from the site. The city
also agreed to close a parking lane on the two roads to allow
for deliveries to the site.
Because of the tightness of the site, deliveries had to be
carefully coordinated. Approximately 12 trades and 100 people
were sometimes onsite at one time.
"You have to divide up the crew, which means you are
running two separate jobs, so it was difficult keeping your
eye on people," Blum said. "You have to be running
up and down floors but it makes things a little more exciting."
Wrapping Up
Enclosing the twin, six-story structures will be a brick and
cast-stone veneer with a backup of 6-in., 16-gauge metal studs
with a dense glass vapor barrier and rigid insulation that
will create an airspace between the exterior veneer and the
interior metal stud wall. Topping off both buildings will
be a four-ply, built-up asphalt roof with gravel poured on
top.
Some artistic touches will include copper roofs over the bay
windows and a false mansard running the perimeter of the main
roof.
Inside the dorms will be room for 358 students to be housed
in apartments that range from one to eight bedrooms. Also
included in the apartments will be a kitchenette, two bathrooms
and a living room.
The cellars will contain amenities such as a game room and
postal services. The entry floor will consist of a community
room for the general public.
Currently the project is on time with punchlist items being
worked on and should be open by August. N
Iona Transformation Will Continue
While construction wraps up on the new residence halls at
Iona College, more projects are projected for the New Rochelle,
N.Y., campus.
"As a result of the construction of the dorms, we will
lose parking spaces," said George Fountaine, the college's
director of facilities management. "The city is very
sensitive about us having enough spaces for the students and
faculty."
To bring back the parking spaces, two buildings will be demolished
to make room for an expanded parking lot. Fountaine said that
funding for the dormitories and the parking lot has come from
the Dormitory Authority State of New York.
"There will be more students at Iona, so we have designed
a new, 40,000-sq.-ft. student center dubbed the LaPenta Student
Center," he added. It will be located in the middle of
the campus and will accommodate student activities as well
as house a cafeteria and computer rooms.
In addition, an extension of the Hynes Athletic Center will
be built for intramural sports and will house a rowing tank,
basketball courts, cardio rooms, locker rooms, 15 offices,
a conference room and a recreation room.
"The current facility, the Mulchahy Center, has been
overrun with varsity sports," said Fountaine. In addition,
he said that college coaches were working out of cubicles;
now they will have 10- by 10-ft. offices.
An extension to Ryan Library is also planned. "We are
going to build a two-floor wing on the backside of Ryan Library,
but we don't have any floorplans yet," Fountaine said.
He said the four projects - the parking lot, Hynes Center,
LaPenta Student Center and Ryan Library expansion - are presently
submitted to the city of New Rochelle along with a draft environmental
impact statement. "We hope to be on the planning board
in May so we can get the process going," Fountaine added.
Funding for the Hynes Center, LaPenta Student Center and Ryan
Library expansion is dependent on the outcome of a capital
campaign. Fountaine said if all the money comes in at once,
LaPenta and Hynes will be the first projects constructed.
|