Spence
School Really Three Projects in One
By Jason Feldman
The 40,165-sq.-ft., five-story Spence School being constructed
on 56 E. 93rd St. on Manhattan's Upper East Side was really
three projects in one - a renovation/historical preservation,
underground construction and an expansion.
Construction on the approximately $30 million project began
in January 2002. "The main challenge was fitting their
program into the existing building envelope," said Jim
Sager, senior associate with Platt Byard Dovell White Architects,
the project's New York-based architect.
The existing building was originally a four-story private
residential mansion that was constructed in the 1930s. In
the early 1970s, Roosevelt Hospital took over the building
and turned it into a drug rehabilitation center.
It was also a landmark building, which meant that exterior
modifications had to be kept to an absolute minimum. "It
was primarily program-driven and we had a limited amount of
space to work," Sager said. The program - what the school
needed and wanted for its growth - consisted of building a
gym, library, 15 classrooms and spaces for music, art, dance,
science labs and a computer lab.
To get what the school needed, Sager had to go up - and down.
Underground Gym
The gym became the underground element of the construction.
Because the gym was in the program, and the existing building
did not have the capacity for it, there was only one way to
go: down.
To construct the gym, crews pounded 35 ft. deep into rock
with hydraulic hammers.
Removing the rock was difficult because only one lane of
traffic was closed on 95th Street. "To remove the excavation
materials, a hole was dug in the sidewalk and the materials
were pushed to the hole and lifted out," Sager said.
"The excavation took one year," added Robert Trostle,
senior project manager for F.J. Sciame Construction Co. Inc.,
the project's New York-based construction manager.
The excavation and foundation construction was a separate
bid package. Trostle said that the project was broken up into
two phases so workers could get an early start. The first
was the excavation and foundation work and all work up to
the underside of the second floor.
The second phase was all the work from the second floor to
the new fifth floor, which consisted of restructuring the
existing building, interiors and adding a fifth floor.
Noise and fumes presented problems to many in the primarily
residential neighborhood during excavation. The solution was
to shift work hours from 7 a.m. to 6 p.m., to 8 a.m. to 5
p.m. shift work hours.
"Now that the building is semi-enclosed, the noise and
dust has been minimized," Trostle said.
The foundation work consisted of 12-in.-thick, cast-in-place
concrete walls with heavy steel rebar that was built after
shoring up the foundations of the surrounding buildings. In
addition, the north end of the excavation required some shoring
of the existing building.
"Caissons were drilled underneath the rock to seat the
building," Sager said.
Also supporting the building will be a large steel truss
that is 12 ft. deep and 80 ft. long that spans property lines
and runs down the center of the gymnasium. "The truss
had to be built onsite because it was too big to transport
whole," Trostle said.
Sager added, "The truss was able to eliminate some additional
shoring to the building because the contractor had an idea
to integrate some of the columns into the truss."
Tying In
Tying in the new elements into the structure make up the project's
second and third elements - a historic preservation/renovation
and expansion.
Structurally, the exiting building was steel frame and limestone,
but the framing system had to be overhauled. To thread the
new steel into the old building, Trostle said: "We had
to remove the main structural column - after shoring - then
placed a new column and tied in with new beams. This was done
throughout the entire structure."
To thread the new steel members, holes were chopped into
the floor and then the affected beams would be shored up.
Additionally, a new flooring system was installed that consists
of concrete with a metal deck.
Although the exterior could not be altered significantly,
the windows could be replaced by Thermopan units with a profile
that matched the existing façade profile. "Working
with the landmark, we made calculated additions to the exterior,"
Sager said.
However, not much of the exterior changed. "The existing
slate roof was carefully removed and reused as well as existing
limestone chimneys," Trostle added.
In the interior, many elements were carefully restored, including
the wooden molding, and existing plaster details were molded
so that they can be recast.
"There were a series of existing spaces that we identified
as the heart and soul of the interior and we tried to preserve
them, like the lobby," Sager said. "Our intent was
to preserve the space and transition to a more modern vocabulary."
That modern vocabulary is the fifth floor, which is set back
from the original building and will be enclosed by a new material
called a turncoated stainless steel panel system.
"We chose that material to be sympathetic to the original
structure, but we wanted something a little different,"
Sager said.
Construction is currently on schedule and is expected to
be completed by July.
|