|
DeKalb Avenue Station Undergoes Rehabilitation
88-Year-Old Station Will be ADA Compliant
by Jason Feldman
The 88-year-old DeKalb Avenue station in downtown Brooklyn
is undergoing a $38.8 million modernization.
The DeKalb station has seen several modifications over the
years, but none was this extensive. This renovation will also
make the station compliant with the Americans with Disabilities
Act through the installation of an elevator from the street
level.
Yet that is only one part of the work. Far more time and
labor will be spent restoring the station to its former grandeur,
complete with mosaic tiled walls.
Work began in August 2001, and safety was a priority from
the start. Nir Golan, project manager for Valley Stream, N.Y.-based
Gottlieb Skanska/Slattery Skanska, the project's joint venture
construction manager, said work was not allowed during the
day because of the constant movement of trains (and people)
in and out of the station.
The Metropolitan Transportation Authority/New York City Transit
diverted trains between 11 p.m. and 5 a.m. and on weekends
to allow for construction. "We were allowed to work during
those times and it meant that we had to be ready to go at
11 and have everything cleaned up by 5 a.m.," Golan said.
In addition, safety meetings are held weekly to review procedures
and keep the crews alert to all possibilities.
Tight Fit
Probably the most difficult part of the work is the demolition
and reconstruction of the entrance on the southeast corner
of DeKalb and Flatbush avenues. The design calls for the installation
of an elevator from the street level to the mezzanine, constructing
two elevators from the mezzanine to the platforms and reconstructing
the staircase from street level to the mezzanine.
Complicating matters is the fact that the entrance to the
station is through a corner overhang of the New York Telephone
Building at DeKalb and Flatbush avenues.
"The building could not be disturbed," Golan said.
Workers were able to use the building's parking garage to
get access to the staircase. Avoiding the overhang required
a 45-ton crane to carefully place the structural steel. Extensive
seismic monitoring ensured that the building would not be
disturbed.
Also hindering work was an existing NYCT ductbank and manhole
on the sidewalk, which travels over the top of the roof, said
Jim Wright, project manager for New York-based Lee Harris
Pomeroy Architects, the project's architect.
To install the elevators, the north wall of the south mezzanine
had to be expanded and the roof had to be reconstructed, he
added.
A solution was to reconstruct the manhole and structurally
frame the north wall around it, Wright said. This led to a
curved wall that will be covered with artwork as part of the
MTA's Arts-for-Transit program.
"We developed an architectural concept that ties everything
together, so we repeated the curved wall for the north mezzanine
as well," Wright said.
He added that getting this part of the work done first was
a way to speed up construction. "Working with the TA,
the phasing was set up so the most difficult part of the project
was handled first," Wright said. "By attacking the
hard part earlier we gain momentum and minimize delays."
As of the end of March, work had been completed on the southeast
exit.
Bringing it all Back
On the platform level extensive work will be needed to bring
back the grandeur of the station. The tiles along the walls
were seriously damaged as a result of water infiltration over
the decades.
There used to be skylights in the sidewalk that brought sunlight
into the station. "They were just slabbed over with concrete
during the 1940s," said Wright. The problem is that the
concrete slabs were not waterproofed. Another major leakage
problem came from cracks in the station's walls that also
let in water.
To permanently stop the water, the slab that covered the
skylights was dug up, waterproofed and re-poured. A grout
was used to plug the cracks throughout the station.
As the water infiltration gets mitigated, work will begin
on restoring the mosaic tiled walls. "During the design
phase, we did an extensive survey of the mosaic surfaces,
which led us to replace most of the tile on the walls,"
Wright said. The walls also required the removal of nine decades
of accumulated soil and soot.
The floor tiles will also be replaced, new lighting will
be installed and there will be a new communication system.
An extensive security system will be set up as well.
"There is an attention to security by increasing the
surveillance and removing visual obstructions, placing security
cameras where an employee is not present," Wright added.
He said that by the time the project is finished, people
will want to use the once dilapidated DeKalb station.
The project is on time and is expected to be completed in
October 2004.
|